Please see the below update with regards to maintenance work on the M54.
Due to unforeseen circumstances, our programme of work has changed.
The remainder of our M54 concrete repair work will now be carried out as follows:
Thursday 27 March from 8pm to 6am, and then Friday 28 March from 8pm to 6am Monday 31 March – M54 eastbound junction 4 to junction 2 closed.
Thursday 3 April from 8pm to 6am, and then Friday 4 April from 8pm to 6am Monday 7 April – M54 eastbound junction 4 to junction 2 closed.
Thursday 10 April from 8pm to 6am, and then Friday 11 April from 8pm to 6am Monday 14 April – M54 westbound junction 2 to junction 3 closed.
Thursday 17 April from 8pm to 6am, and then Friday 18 April from 8pm to 6am Monday 21 April – M54 westbound junction 2 to junction 3 closed.
We’ll need to return to carry out further work on the M54 eastbound between junction 5 and junction 4. Our work will take place during weeknight closures. We’ll share further information via our M54 mailing list once our programme is confirmed.
We have carefully considered the delivery of this work. Our full weekend closures will enable us to carry out our work safely and allow the concrete to set to the required strength. We apologise for the short notice.
What does this mean for you?
During our work, we’ll install fully signed diversion routes which have been agreed by the local authority.
Emergency vehicles will have access throughout.
We’ll make every effort to ensure the impact on the local community and travelling public is kept to a minimum. We always aim to work to the programme, however unforeseen circumstances or adverse weather conditions may mean changes.
Find out more
We plan to carry out further resurfacing work at this location, we’ll write to you again at the earliest opportunity.
If you’d like to be kept up to date with future works along the M54, please subscribe to our mailing list by emailing noreplyM54WMids@nationalhighways.co.uk .
While we work at this location, we’ll have a dedicated public liaison officer (PLO) available to answer any questions that may arise. If you have any questions, or if you would like to know more about our work, please call us on 0300 123 5000 or email info@nationalhighways.co.uk.
You can also visit our website at nationalhighways.co.uk/our-work/ or write to us at National Highways, National Traffic Operations Centre, 3 Ridgeway, Quinton Business Park, Birmingham, B32 1AF.